When Is The Deadline Date For Planning Board Submissions?

Every application type has different submittal requirements.  A Subdivision Approval Not Required Plan (SANR) must be submitted at least five (5) days in advance of the Board meeting for consideration at the meeting.  Other application types have different submittal requirements depending upon the type of application.  A Public Hearing on a Special Permit must be held within sixty five days of date of submittal, a site plan must be finally acted upon within ninety days following the close of the Public Hearing, a preliminary plan must be finally acted upon within forty-five days of submission and a definitive plan must be finally acted upon within ninety days of submission (when the plan is preceded by a preliminary plan).